Work has now started on site. The developers are moving in the site offices and facilities, the earth moving equipment and constructing a temporary entrance.
The first part of the site (the field nearest the entrance on Ash Lodge Drive) has been completely fenced off and security established around the site compound. Work to remove the trees between the fields nearest the school has been started and excavation of the first of the drainage ditches has begun. This ditch has been connected to the existing drain running behind Ash Lodge Drive.